Quiz questions: in English
Example question: In a project network for implementing a transport information system, what does the total float of an activity represent? The duration by which the activity must be accelerated, The amount of equipment assigned to the activity, The probability that the activity will be completed early, The time the activity can be delayed without delaying the project completion